Construction Pre-Works, Community Engagement

Summerlea board members Christine Belter and Rusk Redmond regularly attend the meetings of the City of Edmonton’s LRT working group to receive the latest information and updates about the Valley Line West LRT and everything related to it. Here are the messages from the most recent meeting:

  • This year’s activities include the preliminary boreholes and site laydown.
  • The temporary transit centre, which is planned for the overflow parking lot along 90th Avenue, is a City of Edmonton project (not in the scope of the Marigold consortium who are building the LRT).
  • The City LRT communications is willing to give us two information sessions in May for Summerlea residents. They are proposing the last week in April, so stay tuned.

The latest construction notice details the pre-works starting on March 29 on 87 Avenue, 156 Street, Stony Plain Road, 104 Avenue, and 102 Avenue.